Grant

Project 4

Project: New Switch House Building & Compound Area

Location: St. Marychurch Substation, Torquay

Client: Western Power Distribution

Role: Principal Contractor

Duration: 12 weeks

Grant Construction was engaged by Western Power Distribution to construct
a new, traditional, switch house building within a walled compound, in an
urban area, adjacent to a busy road. The work was completed during the
winter but despite the adverse weather conditions, was still delivered within
the allotted timescale.

Additional work included a pocket substation base and above ground earthing.

Particular care was necessary when forming the substructure adjacent high
boundary walls.

 

 